Construction work runs on credit. A contractor buys materials, pays workers and subcontractors, and is paid weeks or months later. When the payment does not arrive, or when an owner is told that a lien has been registered against their property, both sides face a problem with a clock attached to it.
In Ontario, a construction lien is a legal claim against a property for unpaid work or materials. It is a powerful tool because it attaches to the land itself, not just to a person, and it is also one of the most deadline driven areas of law. A lien that is registered a few days late, or not followed up in court, can disappear.
This guide explains how construction liens work in Ontario under the Construction Act: who can claim one, the key deadlines, how holdback protects owners, how prompt payment and adjudication work, and how a lien is discharged. It is written for contractors, subcontractors, suppliers, homeowners and investors, and is a companion to our guides on condo law in Ontario, buying a home in Ontario and small claims court in Ontario. It also explains how to find a real estate lawyer in the GTA who speaks your language.
Meet Our Real Estate Lawyers
What Is a Construction Lien
A construction lien is a security interest in a property that a person can claim when they have supplied services or materials to an improvement on that property and have not been paid. The Construction Act, Ontario’s main law on the subject, gives this right to people who work on or supply to a project, even when they have no direct contract with the owner.
The lien does not mean the owner automatically owes the money. It is a claim that must be proven, and the owner or others may dispute it. But while a lien is registered on title, it can make it difficult or impossible to sell or refinance the property, which is why it creates strong pressure to resolve the dispute.

Who Can Claim a Lien
Lien rights extend down the chain of contracts on a project. Typically the people who can claim one include:
- General contractors who have a contract with the owner.
- Subcontractors who work for the general contractor or for other subcontractors.
- Suppliers who provide materials, even if they never visit the site.
- Workers and labourers for unpaid wages, within limits.
- Architects, engineers and others who provide services to the improvement.
People who sell off the shelf goods without connection to a project, or who work on something that is not an improvement to land, generally do not have lien rights. Lien rights also cannot be given up in advance by contract in most cases, so a clause in a contract that tries to waive them may not hold up.
The Key Deadlines
Timing is everything in a lien claim. There are two main steps: preserving the lien, and then perfecting it.
| Step | What Happens | General Deadline |
| Preserve the lien | Register a claim for lien on title to the property | Within 60 days after the last day of supply or the date of the event that starts the period, such as publication of a certificate of substantial performance |
| Perfect the lien | Start a court action to enforce the lien and register a certificate of action on title | Within 90 days after the last day for preserving the lien |
| Lien expires | If a lien is not preserved or perfected in time, it expires and can be removed from title | Automatically after the deadline passes |
The start date of the 60 day period depends on the type of contract, the nature of the work, and events such as the publication of a certificate of substantial performance, a contract being terminated, or a contract being abandoned. Getting the start date wrong is one of the most common ways lien rights are lost. Because the period is short and the counting rules are technical, speak to a lawyer immediately when payment problems arise, and do not wait for the project to end.
A Practical Warning About Counting
Do not assume that the clock starts on the date of your last invoice, the date you stopped working, or the date you were told the job was over. In many cases it does not. Keep records showing exactly when work and supply ended, and ask a lawyer to confirm the date before you rely on it.

Holdback: How Owners Protect Themselves
Owners are required to hold back a portion of each payment they make under a construction contract. This holdback is generally 10 percent of the price of the services and materials supplied. It acts as a pool of money that is available to pay lien claimants if the contractor does not pay the people below them.
- An owner who properly retains the holdback is, in most cases, liable for lien claims only up to the amount of the holdback.
- An owner who fails to hold back can be personally liable for more, which is a serious risk for homeowners and developers.
- The holdback is generally released 60 days after a certificate of substantial performance is published, as long as no liens have been registered.
A lien claimant can only claim against the holdback if they preserve their lien on time. That is one more reason the deadlines in the previous section matter.
Prompt Payment and Adjudication
Ontario’s Construction Act also sets a prompt payment system, applying to most construction contracts. Broadly, an owner must pay a proper invoice from the contractor within 28 days. If the owner disputes the invoice, they must give a notice of non-payment within 14 days, explaining the reasons. Contractors must pass payment down the chain within set periods too. If you are in a payment dispute, you can ask for a quick, interim decision from an adjudicator through a process designed to be faster and cheaper than going to court. The adjudication must be started within 30 days of the event that triggers the dispute. Contracts valued at higher amounts and those with large subcontracting chains are especially likely to use it. For smaller claims that do not involve a lien, see our guide on small claims court in Ontario.
Adjudication decisions are binding on an interim basis, which means you must comply with them even if you plan to challenge the result later. This makes the process an important tool for cash flow, but it also means a missed deadline can cost money fast.
Homeowners and Renovations
Homeowners who hire a contractor for a renovation are owners under the Act, with the same obligations to hold back and the same risks if they do not. Practical steps to protect yourself include a written contract, paying only against invoices, holding back the required 10 percent, asking for proof that subcontractors and suppliers have been paid, and searching the title for registered liens before the final payment. If you are purchasing a property, a lien search is part of the process; see our guide on buying a home in Ontario for what your lawyer checks before closing.
Condominium Projects
Liens also arise in condo buildings, both for work done on individual units and for work done for the corporation. Special rules apply to how a lien can be registered against condominium units and the common elements, and a lien from a contractor working for the corporation can affect all unit owners. See our guide on condo law in Ontario for how condominium corporations operate, and get advice before a lien is registered or a payment is withheld.
How a Lien Is Discharged
A lien can be removed from title in several ways.
- Payment or settlement: the claimant is paid, signs a release, and the lien is discharged.
- Expiry: the lien was not perfected in time, so it expires and the owner can ask to have it removed.
- Payment into court or posting security: the owner or another party pays money into court, or posts a bond or letter of credit, in an amount set by the Act (generally the amount of the lien plus an allowance for costs), and the court orders the lien removed from title. The dispute then continues against the security rather than the land.
- Court order: the court dismisses or vacates the lien, for example because it was improperly registered or the claim has no merit.
A claimant should be careful: registering a lien that is unreasonably large or has no basis can expose the claimant to costs and damages. Do not register a lien for more than you can justify.

What Happens in Court
A lien action is a civil lawsuit, with its own procedures set by the Construction Act, usually in the Superior Court of Justice. It may include a trial or a referral to a master. The court can decide who is owed what, order the property to be sold if the debt remains unpaid, and distribute the proceeds according to priority. Claims often settle, especially once the property is under pressure from a registered lien.
Lien claimants rank in a priority scheme that also interacts with mortgages and other registered interests, so the order of payment is not always obvious. Early legal advice helps contractors decide whether a lien, an adjudication, a court action, or a negotiated payment plan is the best route.
Newcomers and Small Contractors
Many contractors, tradespeople and small renovation companies in the GTA operate with informal contracts and handshake agreements, and some are newcomers who are less familiar with the lien system. Missing a 60 day deadline because of a language barrier or unfamiliarity with the rules can mean giving up a legitimate claim. Owners from newcomer communities who hire contractors also face the risk of not holding back or of signing contracts they have not fully understood.
If you are starting or running a trades business, see our guide on starting a business in Ontario for the legal basics of contracts, insurance and structure.
Why a Construction Lawyer Who Speaks Your Language Matters
A lien case is built on documents: contracts, invoices, change orders, delivery slips and emails. It is also built on timing, and a small misunderstanding about a date can be costly. Explaining the history of a project accurately to a lawyer, and understanding what the lawyer tells you about deadlines and options, is much easier in your first language.
A real estate lawyer who speaks your language can help you act within the deadlines, prepare the right documents, and weigh the cost of a lien against the amount at stake. Our Language Guides explain the legal landscape for specific communities across the GTA, including Mandarin, Cantonese, Hindi, Punjabi, Urdu, Tamil, Korean, Italian, Portuguese, Ukrainian, Russian, Hebrew, Farsi, Arabic, Spanish, and French. For a general guide on finding a multilingual lawyer, see our guide on how to find a multilingual lawyer in Toronto.
How to Find a Construction Lawyer in the GTA
Because lien deadlines are short, contact a lawyer as soon as a payment problem appears. Visit the main lawyers directory, filter by Real Estate Law (or Civil Litigation) and your language, and narrow by location. For advice on choosing a lawyer, see our guide on questions to ask before hiring a lawyer, and for what to expect at your first meeting, see our guide on the first legal consultation. Before you meet, our guide on how to prepare for a legal case explains how to organize contracts, invoices and correspondence. For legal fees, see our guides on how much a lawyer costs in Ontario and retainer agreements in Canada. If cost is a concern, see how to get legal advice in Ontario. Always confirm the lawyer is currently licensed by checking our verification process or the Law Society of Ontario’s public register.
Frequently Asked Questions
How long do I have to register a construction lien in Ontario?
Generally, a lien must be preserved by registering a claim for lien on title within 60 days after the last day of supply or after the event that starts the period, such as the publication of a certificate of substantial performance. It must then be perfected by starting a court action and registering a certificate of action within 90 days after the last day to preserve. These periods are short and the start date can be technical, so speak to a lawyer immediately.
What is holdback and why does it matter?
Holdback is the portion, generally 10 percent, of each payment that an owner must keep back during a construction project. It protects subcontractors and suppliers if the contractor does not pay them, and it limits the owner’s liability for liens if it is properly kept. An owner who does not hold back can be personally liable for more. The holdback is generally released 60 days after a certificate of substantial performance is published, if no liens are registered.
Can a subcontractor or supplier claim a lien if they have no contract with the owner?
Yes. Lien rights extend down the chain of contracts on a project, so subcontractors and suppliers who were not paid can usually claim a lien against the property even without a direct contract with the owner. They must still meet the deadlines and show that they supplied services or materials to the improvement.
How can a homeowner remove a construction lien from their property?
A lien can be removed by paying or settling with the claimant and obtaining a discharge, by letting it expire if it was not perfected in time, by paying money into court or posting security such as a bond, or by a court order dismissing it. If you are selling or refinancing, get legal advice quickly, since a lien can block closing. See our guide on buying a home in Ontario for how title searches work.
What is prompt payment and adjudication under the Construction Act?
Prompt payment rules require owners to pay a proper invoice within 28 days and to give notice within 14 days if they dispute it, with payment passed down the contract chain within set periods. If a payment dispute arises, a party can start adjudication, a faster and cheaper process in which an adjudicator makes an interim binding decision. Adjudication generally must be started within 30 days of the triggering event.
Find a Construction Lawyer in the GTA Who Speaks Your Language
A lien dispute can tie up a property, a payment, or a business. Having a real estate lawyer who can explain your deadlines and options clearly in your first language can protect what you are owed or what you own.